16.
|
You can view the clash statistics discipline-by-discipline at the Clash Manager Form.
Refer to Viewing Overview of Clash Data. |
18.
|
The actions at the Clash Manager Configuration Form described in the previous steps, in general, would not be repeated. However, if significant changes have to be made at this form, recomputation must be performed at the Clash Manager - Clash Recomputation Form, which, in these circumstances, is automatically displayed.
|
19.
|
When changes are made to the Model, it is necessary either to perform Clash Recomputation or to re-run all affected Clash Sets, in order to update Clash Manager data. The Clash Manager - Clash Recomputation Form is not automatically displayed following a change in model, and must be accessed manually to enable recomputation to be performed.
Refer to Advanced Tasks. |
20.
|
As more Clash Sets are run, the statistics displayed at the Clash Manager Form apply to the combination of all Clash Sets. This information, applicable to the current date, can be stored as a 'Milestone' for future reference in determining the progress made on the project. The creation of the Milestone is by selecting 'Track Changes' at the Clash Manager Options Form - Advanced Tab. Milestones can be created, as required.
Refer to Advanced Tasks. |